As part of the City of Albany’s 2024/2025 capital works programme, a concrete footpath will be constructed on Seymour Street (from Collingwood Road to Nelson Street), Nelson Street (from Seymour Street to Wakefield Crescent) and Wakefield Crescent (from Nelson Street to McLeod Street).
Works are scheduled to start in late March 2025 and expected to be completed by early June 2025, weather permitting. The City will endeavour to keep disruptions to a minimum and would appreciate your co-operation in working with on-site staff.
Enquiries should be directed to Anthony Henderson, Team Leader – Civil Infrastructure, (08) 6820 3982 during business hours.